Every estimate you build for a job you were never going to win costs you a job you could have won. A simple, repeatable bid/no-bid check gets you to "yes" or "no" in under an hour, before the real estimating starts.
1. Why bother with a formal check
Most contractors decide by gut feel and by whatever tender landed on the desk most recently. That works until the estimating team is buried in bids that were never a fit, and the good job closes before anyone gets to it. A short written check does two things: it stops weak bids early, and it gives everyone the same reasons for saying no.
2. Hard stops
Check these first. If any one fails, the answer is no, and you've saved the whole estimate.
- Bonding. Does the job need bid, performance, or payment bonds beyond your capacity?
- Prequalification. Safety certification, minimum experience, or prequalified bidder lists you aren't on.
- Mandatory meetings. A mandatory site meeting that has already passed or that you can't attend.
- Time to estimate. The close date against the hours this estimate really needs, including sub and supplier quotes.
- Licensing or insurance requirements you can't meet before close.
3. Fit
- Scope. How much of the work do you self-perform? A job that's 80% your own work is a different bid than one that's 30%.
- Size. Is it inside your usual range? Jobs far above it strain cash flow and bonding. Jobs far below it often aren't worth the overhead.
- Location. Travel, accommodation, and local subs and suppliers. Price the distance honestly.
- Type of work. Have you built this kind of thing before, and can you show it?
4. Capacity
- Will your crews and equipment be free during the construction window, or is this job competing with work you already have?
- Who would run it? A job without a project manager or superintendent available is a no, however good it looks.
- Does the schedule land in a season that suits your work?
5. Risk
These come out of the documents, so this is where a proper read of the package pays off.
- Liquidated damages, and whether the schedule makes them likely.
- Payment terms: pay-when-paid clauses, holdback release, and the owner's payment history.
- Ground conditions and how much risk the contract puts on you.
- Unusual warranty, maintenance, or design responsibility.
- Incomplete documents: missing drawings, conflicts between specs, a geotech report that doesn't cover your work.
6. Winning odds
- Competition. How many contractors pulled the documents or attended the site meeting? Ten bidders on a small job is a coin toss with worse odds.
- Evaluation. Lowest price, or weighted criteria? If weighted, what are your strengths in the non-price points?
- Owner. Have you worked for them before? Owners with a good working relationship are worth more than one job's margin.
7. A simple scoring sheet
After the hard stops, score each area from 1 to 5 and keep the sheet with the tender file.
| Area | Score 1 to 5 | Notes |
|---|---|---|
| Fit: scope, size, location, type | ||
| Capacity: crews, equipment, people to run it | ||
| Risk: contract, ground, schedule, documents | ||
| Winning odds: competition, evaluation, owner | ||
| Strategic value: new client, keeps crews busy, new market |
Pick a line in advance, for example: bid at 18 or more, talk it through between 13 and 17, pass below 13. The exact numbers matter less than using the same sheet every time. After a season, compare your scores to what you won and adjust.
8. Saying no well
If you pass on a job from an owner or general contractor you want to work with, tell them. A short note saying you're passing this one and want to see the next one keeps you on the bidders list. Silence often takes you off it.
Where BidSnap fits: BidSnap doesn't make the bid/no-bid call. It gets you the facts for this check fast: bonding and prequalification requirements, the close date and mandatory meetings, your scope against the trades you self-perform, and the contract and ground risks, each linked to its page. On most packages the overview is ready in under a minute. See how the tender review works, and your first one is free.