How to Read a Geotechnical Report Before You Bid

For anyone moving dirt, the geotech report is the most important document in the package, and the one most often skimmed. Here is what to pull out of it, in the order that matters for your price.

1. What's in a geotech report

Most reports follow the same order. Each part answers a different pricing question.

SectionWhat it tells you
Introduction and scopeWhat the engineer was asked to look at. Anything outside it wasn't investigated.
Field investigationHow many boreholes or test pits, how deep, and when. The date matters.
Borehole logsThe actual ground, layer by layer. This is the evidence; everything else is interpretation.
Lab resultsMoisture content, plasticity, grain size, sulphates. These tell you whether the native soil can be reused.
Subsurface conditions and groundwaterThe engineer's summary of the logs.
RecommendationsSite preparation, excavation, backfill, foundations, frost protection, pavement. Often copied into the spec.
LimitationsWhat the engineer is not responsible for. Read it like a list of your risks.

2. Check the coverage first

Before reading any results, put the borehole locations next to your work.

  • Are there boreholes where your deep excavation actually is? A report that stops 200 m short of your trench line is a guess about the part that matters.
  • Are the boreholes deep enough? A borehole that ends at 3 m tells you nothing about a 5 m sewer.
  • How old is the investigation? Older reports, or ones done for a different site layout, may not match the current design.

3. Read the borehole logs yourself

Each log is a column showing depth, soil description, and test results. The things to look for:

  • Soil description. Clay, silt, sand, gravel, till, fill, organics. Fill and organics are trouble: unknown material, often unsuitable, often more of it than the logs show.
  • SPT N-values (blows per 300 mm). Low numbers mean soft or loose ground: poor bearing, unstable trench walls, equipment that sinks. Very high numbers or refusal can mean cobbles, boulders, or bedrock.
  • Moisture content. Compare it to the plastic limit or the optimum moisture in the lab results. Clay well above optimum won't compact without drying, and drying takes time and space you may not have.
  • Groundwater. Note where water was hit, whether it came in fast, and whether the level was measured on completion or days later in a standpipe.
  • Sloughing or caving notes. If the drill hole wouldn't stay open, your trench won't either.

4. Groundwater: the date is half the story

A groundwater reading is a snapshot. Readings taken in late summer or fall understate spring conditions, sometimes by a metre or more. Ask three questions:

  • When was it measured, and how does that compare to when you'll be digging?
  • Was it a single reading at the end of drilling, or monitored over time?
  • Does the report say anything about seasonal high water?

If your excavation goes below the measured water level, price dewatering, and check whether the spec makes dewatering your design responsibility.

5. Can you reuse the native soil?

This is often the biggest number in an earthwork bid. Import and haul-off costs add up fast.

  • Look for the engineer's statement on whether excavated material is suitable for backfill, and under what conditions.
  • Wet clay may be suitable "if moisture-conditioned." Price the conditioning, or price import.
  • Organic or mixed fill is almost always unsuitable. Estimate its volume from the logs and price disposal.
  • Check the spec against the report. If the spec calls for imported granular backfill where the report says native is fine, the spec usually wins.

6. The recommendations that change your price

  • Subgrade preparation: how deep to sub-excavate under footings or slabs, and what to replace it with.
  • Excavation slopes and shoring: recommended side slopes, or a statement that shoring is needed. Remember the excavation rules in your province's OHS code apply either way.
  • Compaction: required density and lift thickness for each material.
  • Frost protection: frost depth and insulation requirements for shallow utilities and footings.
  • Sulphate exposure: high sulphates mean sulphate-resistant concrete for anything in contact with soil, including manholes and structures.
  • Winter work: restrictions on placing fill or concrete on frozen ground.

7. Read the limitations as a risk list

The limitations section explains that conditions between boreholes may vary and that the engineer isn't responsible for interpretation. Then check the contract. If the contract says the geotech report is "for information only" and the contractor takes the risk of subsurface conditions, everything the report doesn't cover is your contingency.

Where BidSnap fits: BidSnap reads the whole geotech report, including the borehole logs, and pulls out the groundwater readings and their dates, soft or wet layers, reuse statements, and the recommendations that affect your trade, each linked to its page. It also flags when the spec and the report disagree. See how the tender review works, and your first one is free.